🚧 Resurfacing Works Update 🚧

We’re pleased to share that the carriageway resurfacing is on track to be completed today!

A huge thank you to all residents for your patience during these essential works and for moving vehicles when required.

  • Newcastle Drive: Works that began last week will be finished later today, and the road will be fully re-opened.
  • Lenton Road: Planing was completed yesterday, and the team is laying Tarmac today.
  • Park Drive & Fishpond Drive: These sections will be planed and completed today, provided there are no unexpected issues.

👏 Special thanks to Ainsley Asphalt and Stardom Limited for their hard work and professionalism throughout this project.